Operations Management: Production Systems, Facility Location and Layout, ERP, Scheduling, Quality Management and Operations Research
2. Enterprise resource planning and production planning, scheduling and control
Enterprise resource planning (ERP) is an integrated software system that runs the organisation's core processes — finance, human resources, procurement, production, inventory, sales and distribution, CRM — on a single shared database, so that a transaction entered once updates every function in real time. It evolved from inventory control packages through MRP (material requirements planning, 1970s: explode the master production schedule through the bill of materials against inventory records to time purchase and production orders) and MRP II (manufacturing resource planning, 1980s: adds capacity, finance and marketing) to ERP in the 1990s; the term ERP is credited to Gartner. Benefits are integration, a single version of the truth, process standardisation, reduced inventory and faster closing; the risks are cost and time overruns, customisation creep, resistance to change and the 'big bang' cut-over.
- Aggregate planning — medium-term (3–18 months) match of capacity to demand by product family, using overtime, hiring, subcontracting, inventory and backorders; options are chase (vary output to demand), level (constant output, absorb with inventory) or a mix.
- Master production schedule and MRP — what end items to make and when; MRP nets gross requirements against on-hand and scheduled receipts, offsets by lead time, and releases planned orders.
- Loading — assigning jobs to work centres; the Gantt chart (Henry Gantt) shows load against time. Sequencing — the order of jobs at a centre by priority rules.
- Dispatching — releasing orders and instructions to start work; monitoring (follow-up, expediting) — comparing progress with schedule and correcting; input-output control tracks planned versus actual flow at each centre.
- Pull systems — JIT/Kanban (Toyota, Taiichi Ohno) produce only what the next stage withdraws, exposing waste (the seven wastes: overproduction, waiting, transport, over-processing, inventory, motion, defects); the theory of constraints (Goldratt, 'The Goal') schedules to the bottleneck by drum-buffer-rope.
| Rule | Order jobs by | Effect |
|---|---|---|
| FCFS (first come, first served) | Arrival order | Fair, simple; poor on flow time and lateness |
| SPT (shortest processing time) | Smallest processing time first | Minimises mean flow time and mean number of jobs in system; long jobs starve |
| EDD (earliest due date) | Earliest due date first | Minimises maximum lateness (tardiness) |
| CR (critical ratio) | (Due date − today) ÷ remaining processing time; lowest first | Dynamic; ratio below 1 means already behind |
| Johnson's rule | n jobs on two machines in the same order: pick the smallest time; if on machine 1 schedule it first, if on machine 2 schedule it last; repeat | Minimises makespan (total elapsed time) for the two-machine flow shop |
3. Quality management: SQC, quality circles, TQM, Kaizen, benchmarking, Six Sigma and ISO
| Guru | Contribution |
|---|---|
| Walter Shewhart | Control charts (Bell Labs, 1924); the plan-do-check-act cycle in its original form |
| W. Edwards Deming | 14 points for management, the PDCA (Deming) cycle, 'seven deadly diseases', system of profound knowledge; taught Japan after 1950; Deming Prize (JUSE, 1951) |
| Joseph Juran | Quality trilogy (planning, control, improvement); 'fitness for use'; Pareto principle applied to quality (vital few, trivial many); cost of quality |
| Philip Crosby | 'Quality is free'; zero defects; 'conformance to requirements'; four absolutes; 14 steps |
| Armand Feigenbaum | Total quality control (1951/1961) — quality is everyone's job; the 'hidden plant' |
| Kaoru Ishikawa | Cause-and-effect (fishbone) diagram; quality circles; company-wide quality control; the seven basic tools |
| Genichi Taguchi | Quality loss function; robust design; design of experiments for quality |
| Masaaki Imai / Shigeo Shingo | Kaizen (Imai, 1986 book); poka-yoke mistake-proofing and SMED quick changeover (Shingo) |
Statistical quality control (SQC) distinguishes chance (common) causes of variation, inherent in the process, from assignable (special) causes that can be found and removed. Control charts plot a sample statistic against a centre line and control limits set at ±3 standard errors: for variables (measured data) the X̄ chart tracks the process mean and the R chart the range; for attributes the p chart tracks the fraction defective, the np chart the number defective, the c chart the number of defects per unit (Poisson) and the u chart defects per unit for variable sample size. A point outside the limits, or a run of seven on one side of the centre line, signals an assignable cause. Acceptance sampling judges a lot from a sample by a plan (n, c): accept if defectives ≤ c; the operating characteristic curve shows the probability of acceptance against lot quality, with the producer's risk α at the AQL (good lots rejected) and the consumer's risk β at the LTPD (bad lots accepted). Process capability compares the specification spread with the process spread: Cp = (USL − LSL)/6σ ignores centring; Cpk = min[(USL − μ), (μ − LSL)]/3σ penalises an off-centre process; Cp ≥ 1.33 is a common target and Six Sigma implies Cp = 2.
- Quality circles — small voluntary groups of 6–12 workers from one area who meet regularly to identify, analyse and solve work-related quality problems using the seven tools; began in Japan in 1962 (Ishikawa, JUSE); in India the first quality circle was formed at BHEL Hyderabad/Ramachandrapuram in 1981 and the Quality Circle Forum of India (1982, Hyderabad) promotes them.
- Total quality management (TQM) — a management philosophy of continuous improvement in every process, customer focus (internal and external), total employee involvement, fact-based decisions, supplier partnership and top-management leadership; its cost-of-quality logic (prevention, appraisal, internal failure, external failure) shows that spending on prevention cuts total cost; the Malcolm Baldrige National Quality Award (USA, 1987) and the EFQM model (Europe, 1991) are TQM frameworks; in India the Rajiv Gandhi National Quality Award (BIS, 1991) and CII-EXIM Bank Award.
- Kaizen — 'change for the better': continuous, incremental, low-cost improvement by everyone every day, as against innovation's large, costly leaps; tools are 5S (seiri, seiton, seiso, seiketsu, shitsuke — sort, set in order, shine, standardise, sustain), gemba walks, the PDCA cycle and suggestion systems.
- Benchmarking — measuring one's processes and performance against the best (Xerox, 1979, against Japanese competitors and later L.L. Bean's warehousing); types are internal, competitive, functional (same function, different industry) and generic; steps: plan, collect data, analyse the gap, adapt and improve.
- Six Sigma — developed at Motorola (Bill Smith, 1986) and made famous by GE under Jack Welch (1995); a process at six-sigma level, allowing the 1.5σ shift, produces 3.4 defects per million opportunities; the improvement roadmap is DMAIC (define, measure, analyse, improve, control) for existing processes and DMADV/DFSS for new ones; belts — champion, master black belt, black belt, green belt, yellow belt.
- ISO standards — the International Organization for Standardization (Geneva, 1947); ISO 9000 family for quality management systems (first 1987; current ISO 9001:2015, built on seven principles — customer focus, leadership, engagement of people, process approach, improvement, evidence-based decision making, relationship management — and a risk-based, high-level structure); ISO 14001 environmental management; ISO 45001 occupational health and safety; ISO 27001 information security; ISO 22000 food safety; ISO 26000 social responsibility (guidance, not certifiable); in India the BIS is the national standards body and accreditation is through NABCB under the Quality Council of India (1997).
4. Operations research: transportation, assignment, queuing, decision theory and PERT/CPM
Operations research applies mathematical models to decisions; it grew out of military planning in the Second World War (Blackett's team in Britain) and entered industry after 1945. The transportation problem ships from m sources to n destinations at minimum cost. An initial feasible solution comes from the north-west corner rule (start top-left, ignore cost), the least-cost method (fill cheapest cells first) or Vogel's approximation method (VAM: penalty = difference between the two lowest costs in each row and column, allocate in the row or column with the largest penalty — usually nearest to optimal). A non-degenerate basic solution has exactly m + n − 1 allocations; fewer means degeneracy, cured by placing an ε in an empty cell. Optimality is tested by MODI (u–v method): compute uᵢ + vⱼ = cᵢⱼ for allocated cells and the opportunity cost Δᵢⱼ = cᵢⱼ − (uᵢ + vⱼ) for empty cells; all Δ ≥ 0 means optimal, otherwise the most negative cell enters by a stepping-stone loop. An unbalanced problem (supply ≠ demand) gets a dummy row or column with zero cost.
The assignment problem — n jobs to n persons or machines, one each, at minimum cost or time — is a special transportation problem with all supplies and demands equal to 1, solved by the Hungarian method (Kuhn, 1955, after König and Egerváry): subtract row minima, then column minima, cover all zeros with the minimum number of lines; if the lines equal n assign on zeros, otherwise subtract the smallest uncovered element from all uncovered elements, add it at line intersections, and repeat. A maximisation problem is converted by subtracting every element from the largest; an unbalanced one gets a dummy row or column of zeros; a prohibited assignment gets cost M (infinity).
| Measure | Formula |
|---|---|
| Utilisation (traffic intensity) | ρ = λ/μ; probability the server is idle P0 = 1 − ρ |
| Expected number in system | Ls = λ/(μ − λ) = ρ/(1 − ρ) |
| Expected number in queue | Lq = λ²/[μ(μ − λ)] = ρ²/(1 − ρ) |
| Expected time in system | Ws = 1/(μ − λ) |
| Expected waiting time in queue | Wq = λ/[μ(μ − λ)] = Ws − 1/μ |
| Little's law | Ls = λWs and Lq = λWq (hold for any stable queue) |
Decision theory classifies decisions by knowledge of outcomes. Under certainty, one state of nature. Under risk, probabilities are known: choose the act with the highest expected monetary value (EMV = Σ pᵢ × payoffᵢ) or lowest expected opportunity loss (EOL); the expected value of perfect information EVPI = expected payoff with perfect information − best EMV = minimum EOL, and is the most one should pay for a perfect forecast; decision trees (squares for decisions, circles for chance) roll back EMVs from right to left. Under uncertainty, no probabilities: maximax (optimist: best of the best), maximin (Wald, pessimist: best of the worst), minimax regret (Savage: minimise the maximum opportunity loss), Laplace (equal likelihood: highest average payoff) and the Hurwicz criterion (coefficient of optimism α: α × best + (1 − α) × worst).
| Aspect | CPM (critical path method) | PERT (programme evaluation and review technique) |
|---|---|---|
| Origin | 1957, DuPont and Remington Rand (Kelley and Walker), plant maintenance | 1958, US Navy with Booz Allen Hamilton, Polaris missile |
| Time estimates | Deterministic, one estimate; activity-oriented | Probabilistic, three estimates (optimistic a, most likely m, pessimistic b); event-oriented |
| Key formulas | Cost slope = (crash cost − normal cost)/(normal time − crash time); crash the critical activity with the lowest slope first | tₑ = (a + 4m + b)/6; σ = (b − a)/6; project variance = Σ variances on the critical path; Z = (target − expected)/σ |
| Best for | Repetitive projects with known times; time-cost trade-off (crashing) | Research and development, new projects with uncertain times |
Key takeaways
- Production systems run from project and job shop (low volume, high variety, process layout) through batch and mass (product layout, line balancing) to continuous; location uses factor rating, break-even, centre of gravity and the transportation model; cellular layout is the hybrid.
- ERP integrates all functions on one database and grew from MRP and MRP II; SPT minimises mean flow time, EDD minimises maximum lateness, Johnson's rule minimises makespan on two machines; JIT/Kanban pulls, TOC schedules to the bottleneck.
- Deming = 14 points and PDCA; Juran = trilogy; Crosby = zero defects; Ishikawa = fishbone and quality circles (Japan 1962, BHEL 1981); X̄-R for variables, p and c for attributes; Cp = (USL − LSL)/6σ.
- Six Sigma (Motorola 1986) = 3.4 DPMO with DMAIC; Kaizen = continuous small improvement with 5S; benchmarking began at Xerox; ISO 9001:2015 rests on seven principles and ISO 14001 is environmental.
- Transportation: NWC, least cost, VAM for a start, m + n − 1 allocations, MODI for optimality; assignment by the Hungarian method; M/M/1: Ls = λ/(μ − λ), Ws = 1/(μ − λ).
- Under risk choose by EMV, EVPI = minimum EOL; under uncertainty maximax, maximin (Wald), minimax regret (Savage), Laplace, Hurwicz; CPM 1957 DuPont deterministic, PERT 1958 Polaris with tₑ = (a + 4m + b)/6, σ = (b − a)/6, critical path has zero float.
Practice questions (11)
Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.
A layout in which machines are arranged in the sequence of operations on a single standardised product is called:
Show answer
Answer: B — Product layout
Product (line) layout suits mass production; it minimises material handling and WIP but is inflexible and needs line balancing. Process layout groups similar machines; fixed-position brings resources to the product; cellular is the hybrid.Which sequencing rule minimises the mean flow time of jobs at a single work centre?
Show answer
Answer: C — Shortest processing time
SPT minimises mean flow time and the mean number of jobs in the system; EDD minimises maximum lateness; FCFS is fair but poor on both; the critical ratio is a dynamic due-date rule.Johnson's rule is used to:
Show answer
Answer: B — Sequence n jobs through two machines to minimise total elapsed time
Johnson's rule schedules the job with the smallest time first if that time is on machine 1 and last if on machine 2, repeating until all are placed; it minimises makespan for the two-machine flow shop. MODI tests transportation optimality.'Quality is free' and the concept of zero defects are associated with:
Show answer
Answer: C — Philip Crosby
Crosby wrote 'Quality is Free' and championed zero defects and conformance to requirements. Deming gave 14 points and PDCA, Juran the quality trilogy, Ishikawa the fishbone diagram and quality circles.To monitor the number of defects per unit of a product where defects follow a Poisson distribution, the appropriate control chart is the:
Show answer
Answer: D — c chart
The c chart tracks the count of defects per unit (Poisson); the p chart tracks the fraction defective (binomial); X̄ and R are variables charts for the mean and range of measured data.A process operating at the Six Sigma level, allowing the conventional 1.5 sigma shift, is expected to produce how many defects per million opportunities?
Show answer
Answer: C — 3.4
Six Sigma, developed at Motorola in 1986, targets 3.4 defects per million opportunities with the 1.5σ shift; its improvement roadmap is DMAIC. 66,807 DPMO is the four-sigma level and 233 the five-sigma level.In a transportation problem with 3 sources and 4 destinations, a non-degenerate basic feasible solution must have how many allocated cells?
Show answer
Answer: C — 6
The condition is m + n − 1 = 3 + 4 − 1 = 6 allocations. Fewer means degeneracy, handled by an ε allocation; optimality is then tested by MODI.Customers arrive at a single counter at 8 per hour (Poisson) and are served at 10 per hour (exponential). The expected number of customers in the system is:
Show answer
Answer: C — 4
Ls = λ/(μ − λ) = 8/(10 − 8) = 4. Utilisation ρ = 0.8, Lq = ρ²/(1 − ρ) = 3.2, Ws = 1/(μ − λ) = 0.5 hour.The decision criterion that selects the alternative whose worst possible payoff is the best is:
Show answer
Answer: B — Maximin
Maximin (Wald) is the pessimist's criterion — best of the worst. Maximax is the optimist's, minimax regret (Savage) minimises the maximum opportunity loss, and Laplace assumes equal probabilities. Hurwicz blends best and worst by a coefficient of optimism.An activity has optimistic, most likely and pessimistic times of 4, 6 and 14 days. Its PERT expected time and standard deviation are:
Show answer
Answer: B — 7 days and 1.67 days
tₑ = (a + 4m + b)/6 = (4 + 24 + 14)/6 = 42/6 = 7 days; σ = (b − a)/6 = 10/6 ≈ 1.67 days. PERT (1958, Polaris) is probabilistic; CPM (1957, DuPont) uses one deterministic estimate.The critical path in a project network is the path with:
Show answer
Answer: B — The longest duration and zero total float
The critical path is the longest route through the network; its activities have zero total float and its length is the minimum project duration. Crashing shortens it by compressing the critical activity with the lowest cost slope first.